4.5 - Final Productivity Calculation
Enroll to start learning
You’ve not yet enrolled in this course. Please enroll for free to listen to audio lessons, classroom podcasts and take practice test.
Practice Questions
Test your understanding with targeted questions
What is the bucket fill factor?
💡 Hint: Think about how different materials affect bucket efficiency.
What happens when the loader's bucket is overloaded?
💡 Hint: Consider what tipping load means.
4 more questions available
Interactive Quizzes
Quick quizzes to reinforce your learning
What does the bucket fill factor adjust?
💡 Hint: Consider what affects how full a bucket can realistically be.
True or False: A track-mounted loader gives better tractive effort than a wheel-mounted loader.
💡 Hint: Think about different mounting systems.
3 more questions available
Challenge Problems
Push your limits with advanced challenges
A loader has a heaped capacity of 3.0 m³ and fills 75% when handling gravel. Its tipping load is 9000 kg. If the unit weight of gravel is 1600 kg/m³, calculate the productivity in kg/hr for a cycle time of 35 seconds.
💡 Hint: Step through the calculations carefully, converting units where needed.
If a track-mounted loader can carry 10 tons per load, with a tipping load safety factor of 0.35, what is the maximum load it can safely carry?
💡 Hint: Remember the safety factor reduces how much we can load safely.