1.5 - Allocation Criteria
Enroll to start learning
You’ve not yet enrolled in this course. Please enroll for free to listen to audio lessons, classroom podcasts and take practice test.
Practice Questions
Test your understanding with targeted questions
What is the definition of float in project management?
💡 Hint: Think about how delays impact project schedules.
Name one key advantage of understanding the critical path.
💡 Hint: Consider the impact on project duration.
4 more questions available
Interactive Quizzes
Quick quizzes to reinforce your learning
What is critical path in project management?
💡 Hint: Consider what affects overall project timing.
True or False: Float allows flexibility in scheduling activities.
💡 Hint: Think about the impact of delays.
2 more questions available
Challenge Problems
Push your limits with advanced challenges
In a project where three tasks with the following characteristics need to be scheduled: Task 1: Float 1 day, duration 5 days; Task 2: Float 0 days, duration 3 days; Task 3: Float 2 days, duration 4 days. Discuss the scheduling strategy and justify your allocation based on float and duration.
💡 Hint: Prioritize based on float, then duration for efficiency.
Given a project with 4 tasks where A has a latest start time of 2 days, B of 0 days, C of 5 days, and D of 4 days. Discuss how conflicts in resource allocation would be resolved.
💡 Hint: Consider using the latest start time to determine urgency.