1.5 - Allocation Criteria
Enroll to start learning
You’ve not yet enrolled in this course. Please enroll for free to listen to audio lessons, classroom podcasts and take practice test.
Interactive Audio Lesson
Listen to a student-teacher conversation explaining the topic in a relatable way.
Understanding Start Times
🔒 Unlock Audio Lesson
Sign up and enroll to listen to this audio lesson
Today, we’re going to learn about the importance of earliest and latest start times in project activities. Can anyone tell me what earliest start time means?
Isn't it the soonest time an activity can begin?
Exactly! It’s the earliest time an activity can start without any delays. And what about the latest start time?
I think it's the latest time it can start without delaying the entire project.
That's correct! So, if an activity has a float of 3 days, it can be delayed by up to 3 days. Who can summarize why understanding these times is important?
It helps in planning the project efficiently and managing delays!
Well said! These times are essential in managing your project's schedule.
Float and Critical Path
🔒 Unlock Audio Lesson
Sign up and enroll to listen to this audio lesson
Let’s dive deeper into float. Who can explain what float is?
It's how much an activity can be delayed without affecting the project completion!
Exactly! Activities with zero float are critical. Can anyone tell me what the critical path means?
Isn’t it the longest path through the project network?
Absolutely! It’s essential as it determines the minimum project duration. Why do you think we should focus on critical path activities?
Because delaying critical activities directly delays the whole project!
Correct! Prioritizing those tasks helps keep the project on schedule.
Resource Allocation with Constraints
🔒 Unlock Audio Lesson
Sign up and enroll to listen to this audio lesson
Now that we understand float and the critical path, let’s consider resource constraints. What challenges might arise from these limitations?
There might not be enough resources to complete critical activities on time.
And that could lead to delays in project completion.
Exactly! With our example project, we have only 2 cranes for multiple activities. How should we allocate these cranes?
We should give them to the activities with the least float first!
Right! Following the 'least total float approach' helps minimize project delays. Can anyone explain why we might choose float over latest start time?
Float gives a clearer picture of how many days we can afford to delay without impacting other activities!
Good point! Balancing resource allocation effectively is key in project management.
Real Project Application
🔒 Unlock Audio Lesson
Sign up and enroll to listen to this audio lesson
Let’s put this knowledge into practice. Given our crane constraints, how would we allocate them to Activities A, B, and C?
Activity B should get the first crane because it has the least latest start time.
And we can give the second crane to Activity A since it has the second least latest start time!
Excellent reasoning! After Activity B is completed, which tasks become eligible for crane allocation?
Activities E, F, G, and C become eligible since B has completed.
Very good! We continue to follow this process through all activities, ensuring cranes are allocated effectively.
Introduction & Overview
Read summaries of the section's main ideas at different levels of detail.
Quick Overview
Standard
The section outlines the importance of understanding both earliest and latest start times for activities within a project. It discusses the concept of float, the critical path, and the challenges faced when resources are constrained. The least total float approach is recommended for effective resource allocation.
Detailed
In project management, understanding resource allocation is critical for successful project completion, especially when resources are limited. This section explains the distinction between earliest and latest start times of activities A to K within a project network diagram. It elaborates on 'float', which is the time an activity can be delayed without affecting the overall project completion time. The section emphasizes the critical path, consisting of the most vital activities (B, E, and I) that dictate project duration. With resource constraints, particularly the limitation of cranes available for activities, a strategic approach using the 'least total float' method is proposed for resource allocation. By prioritizing activities with the least float and latest start time, project managers can ensure that critical tasks are completed efficiently, minimizing delays. The section culminates with an acknowledgment that due to resource constraints, projects will often face delays, illustrated by the shift in completion time from 20 to 29 days.
Audio Book
Dive deep into the subject with an immersive audiobook experience.
Understanding Float and Activity Timing
Chapter 1 of 6
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
So, earliest start time is how early an activity can be started. And later start time is how delayed an activity can be started without affecting the project completion time. So, that means this particular activity A it start can be delayed by 3 days, but this one affect the project completion time. So this has a float of 3 days. So, how much delay an activity you can accommodate without affecting the project completion time that is called as a float of the activity.
Detailed Explanation
In project management, each activity has a specific time frame for its start and finish. The 'earliest start time' is the earliest point in time that an activity can commence, while the 'latest start time' indicates the latest point it can be postponed without causing delays to the overall project. The 'float' or 'slack' of an activity represents the total days it can be delayed—a float of 3 days, for example, means that the activity can be postponed by up to 3 days without impacting the completion of the project. This concept is crucial for identifying which activities are critical for maintaining the schedule.
Examples & Analogies
Imagine you're organizing a birthday party. If you know that the cake can be baked 3 days before the party without affecting the event, then you have 3 days of float. You can safely push the baking date back by three days, but not more, or you won't have a cake for the party.
Resource Constraints in Project Scheduling
Chapter 2 of 6
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
So, for this particular project, first the network diagram is drawn... But everyone knows this cannot be real case in every project site there will be a constraint of resource, resources are never unlimited.
Detailed Explanation
Initially, project schedules can be created assuming there are unlimited resources available for all activities. However, in real-world scenarios, constraints such as limited machinery or manpower must be considered. For instance, if a project requires cranes for construction but only has two available, this limitation must be factored into scheduling, thus affecting the project timeline based on resource allocation.
Examples & Analogies
Consider planning a school play with a limited number of costumes. If there are only two costumes that multiple characters require, you can't have them all on stage at the same time. You need to schedule the characters to ensure there are no costume conflicts, which can lead to delays in the show.
Critical Activities and Resource Allocation Strategy
Chapter 3 of 6
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
So how to allocate the resources on what criteria we are going to allocate the resources... So, the least total float approach is a common approach followed.
Detailed Explanation
To allocate resources effectively, project managers often use the 'least total float' approach. This means they first focus on activities that have the least amount of float, as these are the most critical to project completion. Activities with zero float are termed 'critical,' and they are prioritized for resource allocation to minimize delays. After critical activities are managed, managers can then allocate resources to those with slightly more float. This minimizes the risk of project delays effectively.
Examples & Analogies
Imagine a high school preparing for exams. Students who need the most help in subjects they are about to fail (zero float) get prioritized tutoring before others who might have passed but still want to improve (more float). This addresses urgent needs first and helps overall performance.
Allocation of Cranes and Managing Idle Time
Chapter 4 of 6
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
So, now on what basis we can allocate the resource to these activities... So, in the beginning, you can see the crane C 1 is allocated to A and the crane C 2 is allocated to B.
Detailed Explanation
The project starts with several activities that require cranes, but only two cranes are available. Therefore, the allocation process begins with identifying which activities require immediate attention based on their latest start times. By allocating the cranes to activities with the least latest start time, project managers ensure minimal idle time for equipment and efficient project progression. This careful management allows for the optimal use of the available resources and keeps the project on track.
Examples & Analogies
Think of it like assigning cars to students for a group project. If two cars are available but three students need to get to the library for research, you would first give the cars to the students with the nearest deadlines. This way, the transportation is maximized, and no student is left waiting too long.
Progress Tracking and Further Allocation
Chapter 5 of 6
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
So now see which are all the next eligible activities for allocation... So after B you can see the crane is allocated to E.
Detailed Explanation
After monitoring the completion of specific tasks, project managers will assess which activities can now proceed based on the completion of pre-required tasks. This process involves checking which activities have become eligible for resource allocation as prior tasks finish. For instance, once Activity B is completed, other activities like E, F, and G may now be ready to start. By continuing with this assessment, the project optimizes its workflow and maintains as much efficiency as possible.
Examples & Analogies
Imagine a team working on a puzzle where one section must be completed to access more pieces. Once the first section is done, members can immediately start working on the next areas. This means keeping everyone constantly busy, reducing downtime.
Conclusion of Resource Allocation Principles
Chapter 6 of 6
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
So, this is the basis on which the allocation is being done... So, with this we are coming towards the end of this lecture...
Detailed Explanation
In conclusion, the allocation criteria based on the least latest start time or total float approach allows for effective management of resources in a project. This strategic approach ensures that critical activities are noted, and resources, like cranes, are allocated efficiently to minimize delays. While delays may still occur due to resource constraints, they can be managed to keep the project within acceptable timelines.
Examples & Analogies
Think of organizing a flight schedule. Airlines prioritize takeoffs based on urgency and runway availability. Even if there are delays, the goal is to minimize the impact on the overall travel schedule, similarly to managing project timelines effectively to meet deadlines.
Key Concepts
-
Earliest Start Time: The earliest point when an activity can start.
-
Latest Start Time: The latest point when an activity can commence without delaying the project.
-
Float: The allowable delay for an activity without impacting the project deadline.
-
Critical Path: The longest sequence of activities determining project completion time.
-
Resource Allocation: Assignment of available resources to various tasks in a project.
Examples & Applications
If Activity A has an earliest start time of Day 1 and a latest start time of Day 3, it has a float of 2 days.
In a project with limited cranes, giving priority to activities with the least float ensures critical tasks are completed first.
Memory Aids
Interactive tools to help you remember key concepts
Rhymes
Float, float, measures the wait; keep your project right on date!
Stories
Once in a land of projects galore, a wise manager named Tim opened a door. He saw activities A through K, all needing cranes to work and play. Tim learned of floats and paths critical, ensuring his schedule was never pitiful.
Memory Tools
Remember: C-F-L (Critical - Float - Latest) to know how to schedule your project.
Acronyms
FLOAT can remind us
- Flexibility
- Limited time
- Overlapping tasks
- Activities in order
- Timeliness.
Flash Cards
Glossary
- Earliest Start Time
The earliest time an activity can begin without any delays.
- Latest Start Time
The latest time an activity can start without delaying the project.
- Float
The amount of time an activity can be delayed without affecting the overall project timeline.
- Critical Path
The sequence of activities that determine the shortest time to complete a project.
- Resource Allocation
The distribution of available resources among various projects or activities.