Recommended Textbooks - 3.1 | 4. Project Network Diagram | Construction Engineering & Management - Vol 1
Students

Academic Programs

AI-powered learning for grades 8-12, aligned with major curricula

Professional

Professional Courses

Industry-relevant training in Business, Technology, and Design

Games

Interactive Games

Fun games to boost memory, math, typing, and English skills

Recommended Textbooks

3.1 - Recommended Textbooks

Enroll to start learning

You’ve not yet enrolled in this course. Please enroll for free to listen to audio lessons, classroom podcasts and take practice test.

Practice

Interactive Audio Lesson

Listen to a student-teacher conversation explaining the topic in a relatable way.

Introduction to Project Scheduling

🔒 Unlock Audio Lesson

Sign up and enroll to listen to this audio lesson

0:00
--:--
Teacher
Teacher Instructor

Today we will start with the fundamentals of project scheduling. Can someone tell me what a project network diagram is?

Student 1
Student 1

Isn't it a visual representation of project activities and their relationships?

Teacher
Teacher Instructor

Correct! It shows activities and allows us to determine start and finish times. Now, what are earliest and latest start times?

Student 2
Student 2

Earliest start time is when an activity can begin, and latest start time is the latest it can begin without affecting the project.

Teacher
Teacher Instructor

Exactly! Let's remember it with the acronym **E-S-L-S**. Can anyone tell me what a float is?

Student 3
Student 3

It’s the time an activity can be delayed without impacting the project time, right?

Teacher
Teacher Instructor

Yes! Great job! Float helps us prioritize tasks during scheduling which we will explore next.

Resource Allocation Strategies

🔒 Unlock Audio Lesson

Sign up and enroll to listen to this audio lesson

0:00
--:--
Teacher
Teacher Instructor

Now that we understand floats, let's talk about resource allocation. Why do we assume resources are unlimited initially?

Student 4
Student 4

Because it simplifies planning before we factor in actual limitations!

Teacher
Teacher Instructor

Correct! But later, we must adapt to resource constraints. Can you name a strategy for allocating limited resources?

Student 1
Student 1

The least total float method allows prioritization based on criticality.

Teacher
Teacher Instructor

Exactly! It prioritizes tasks with the least float. Let’s use an acronym to remember: **L-T-F**. How does assigning resources based on float helo us?

Student 2
Student 2

It reduces the risk of delays for critical tasks.

Teacher
Teacher Instructor

Great point! Always keep critical tasks in mind when allocating resources.

Equipment Loading Chart

🔒 Unlock Audio Lesson

Sign up and enroll to listen to this audio lesson

0:00
--:--
Teacher
Teacher Instructor

There’s a crucial tool we can use—the equipment loading chart. What do you think it helps us with?

Student 3
Student 3

It likely shows how equipment is utilized for the project!

Teacher
Teacher Instructor

Correct! It helps identify periods of idle time for equipment. Why is it important to minimize idle time?

Student 4
Student 4

Minimizing idle time ensures resources are used efficiently, reducing delays and costs.

Teacher
Teacher Instructor

Exactly! Quick recap: the equipment loading chart visualizes our resource allocation to prevent idle moments. Remember this chart as we move next to practical applications.

Introduction & Overview

Read summaries of the section's main ideas at different levels of detail.

Quick Overview

This section outlines the critical elements of project scheduling, including activity duration, resource allocation, and methods for minimizing delays in project completion.

Standard

In this section, we delve into project scheduling techniques with a focus on understanding the critical path, resource constraints, and the allocation of cranes based on a least total float approach. We explore the foundational concepts of critical and non-critical activities, the significance of floats, and how these affect project completion times.

Detailed

Detailed Summary

In this section, we address key aspects of project scheduling and resource allocation. A project network diagram involving activities A through K is analyzed. The diagram indicates the activity duration and is accompanied by the earliest start time and earliest finish time displayed above the arrows, and latest start time and latest finish time below the arrows. The float of an activity is introduced, which is the amount of time an activity can be delayed without impacting the overall project duration. For example, activity A can be delayed by 3 days, allowing for a float of three days.

The section discusses the unrealistic assumption of unlimited resources during scheduling. When resource constraints are applied, the project duration may increase — in this case, from an unachievable 20 days to a revised 29 days.

Resource allocation is approached through the least total float method, wherein resources are prioritized for critical activities (those with a zero float). Examples are provided on how resources should be allocated when there are multiple competing activities for cranes, emphasizing the importance of efficiency in resource utilization. The section concludes by reiterating the necessity to minimize delays, presenting the equipment loading chart as a means to visualize resource allocation and project scheduling effectively.

Audio Book

Dive deep into the subject with an immersive audiobook experience.

Introduction to Resource Constraints

Chapter 1 of 5

🔒 Unlock Audio Chapter

Sign up and enroll to access the full audio experience

0:00
--:--

Chapter Content

For this particular project, first the network diagram is drawn, I mean, the scheduling is done assuming that resources are unlimited.

Detailed Explanation

In project management, the initial scheduling of a project often assumes that there are no limitations on resources. This means that when planning, managers consider the best-case scenario where all necessary resources (like equipment and workforce) are readily available without any waiting time. This assumption helps to create a baseline for understanding the project timeline under ideal conditions.

Examples & Analogies

Think of this like planning a family road trip with no budget constraints. You would select the best places to stop, the fastest routes, and all the sights you want to see, assuming you have unlimited time and funds.

Understanding the Critical Path

Chapter 2 of 5

🔒 Unlock Audio Chapter

Sign up and enroll to access the full audio experience

0:00
--:--

Chapter Content

The critical part of this project is B, E and I; the critical path is nothing but the longest path in a particular project which decides the project completion time.

Detailed Explanation

The critical path in project management refers to the sequence of tasks that determine the minimum time required to complete a project. Activities on the critical path are essential, as any delay in these tasks will directly affect the project's overall timeline. In this example, activities B, E, and I are identified as critical, which means they cannot be delayed without extending the project completion time.

Examples & Analogies

Consider a relay race where each runner must finish their portion for the team to qualify. The runner that takes the longest is critical; if they don’t run their leg quickly enough, the entire team’s time suffers. Similarly, in projects, delays along the critical path increase the likelihood of missing deadlines.

Resource Constraints in Project Management

Chapter 3 of 5

🔒 Unlock Audio Chapter

Sign up and enroll to access the full audio experience

0:00
--:--

Chapter Content

For every activity, we need the crane for the completion of the activity, but the actual availability of the crane is there are only 2 cranes available with us.

Detailed Explanation

In this project, there's a limitation on resources, specifically the number of cranes available for use. Although planning might start with the assumption of unlimited resources, it's crucial to adjust that plan based on actual resource availability. With only two cranes needed for multiple activities, the project manager must carefully allocate these cranes to ensure that the project stays on track while mitigating delays.

Examples & Analogies

Imagine a scenario where a construction site has only two cranes, but three jobs are scheduled to be done at the same time. The manager needs to decide which jobs get the cranes first, ensuring that the most time-sensitive work is prioritized so that the project can continue moving forward.

Allocating Resources Based on Criticality

Chapter 4 of 5

🔒 Unlock Audio Chapter

Sign up and enroll to access the full audio experience

0:00
--:--

Chapter Content

We will go by the simple approach, which is commonly followed in many construction project sites that is least total float approach.

Detailed Explanation

The least total float approach is a strategy where resources are allocated first to the most critical tasks—those with the least amount of slack time or float. Float refers to the amount of time that a task can be delayed without affecting the subsequent tasks or the project deadline. Prioritizing tasks with little to no float ensures that resource usage is efficient and that project timelines are adhered to.

Examples & Analogies

Think of this like prioritizing homework assignments. If you have a project due tomorrow (critical task), you'll work on that first before tackling assignments that are due next week (tasks with more float). This ensures that you meet your immediate deadlines while managing your time effectively.

Resource Allocation Process

Chapter 5 of 5

🔒 Unlock Audio Chapter

Sign up and enroll to access the full audio experience

0:00
--:--

Chapter Content

Activity A, B, and C are starting activities. All three activities require a crane, but you have only two cranes with you.

Detailed Explanation

During the initial phase of the project, multiple activities may require resources at the same time. In the case of the project referenced, activities A, B, and C all require crane access. Since there are only two cranes, a decision must be made regarding which activities will be prioritized for crane usage. The activity with the least latest start time is typically prioritized to avoid project delays.

Examples & Analogies

Envision a restaurant where only two chefs are available to prepare meals, but there are multiple orders in queue. The manager needs to decide which meals to prioritize based on how quickly they can be prepared, ensuring that the most time-sensitive orders are addressed first to keep customers happy.

Key Concepts

  • Project Network Diagram: Represents activities and their interdependencies.

  • Float: Time allowance for delaying an activity without affecting project completion.

  • Resource Allocation: Assigning resources while considering constraints.

  • Critical Path: The vital sequence of activities that defines project duration.

Examples & Applications

In a construction project, if Activity A (foundation laying) has a float of 3 days, it means the project schedule allows for a delay of 3 days without affecting the overall timeline.

When 2 cranes are required for tasks like the ceiling and roof installations, using the least total float method ensures the crane is allocated to the critical task first.

Memory Aids

Interactive tools to help you remember key concepts

🎵

Rhymes

Start on time, let delays be few, float is your friend, and critical path too.

📖

Stories

Imagine a ship sailing across a sea of tasks. Each task must set sail on schedule, but if one task is delayed, it risks losing time, just like our ship can only reach its destination if it follows the right path.

🧠

Memory Tools

Remember E-S-L-S for Earliest Start, Latest Start, helping us keep the flow smooth all through!

🎯

Acronyms

Use **R.A.C.E** for Resource Allocation

Resources - Activities - Constraints - Efficiency.

Flash Cards

Glossary

Project Network Diagram

A visual model that shows the sequencing of project activities and their dependencies.

Float

The amount of time an activity can be delayed without impacting the project's completion date.

Critical Path

The longest path in the project network, determining the shortest possible project duration.

Resource Allocation

The process of assigning available resources to various tasks in a project.

Earliest Start Time

The earliest time an activity can begin, given the start times of prior activities.

Latest Start Time

The latest time an activity can begin without delaying the project completion.

Reference links

Supplementary resources to enhance your learning experience.