Test your understanding with targeted questions related to the topic.
Question 1
Easy
What is the purpose of a project network diagram?
💡 Hint: Think about what a flowchart does for processes.
Question 2
Easy
Define float in project management.
💡 Hint: Consider how delays can impact timelines.
Practice 4 more questions and get performance evaluation
Engage in quick quizzes to reinforce what you've learned and check your comprehension.
Question 1
What does float indicate in project management?
💡 Hint: Focus on how much delay is permissible.
Question 2
True or False: The critical path has activities that can be delayed without delaying the project.
💡 Hint: Consider the definition of the critical path.
Solve 1 more question and get performance evaluation
Push your limits with challenges.
Question 1
A project has activities A, B, and C with durations 4, 8, and 3 days respectively. Activity B is critical. If resource constraints limit work to one crane, how would you schedule these activities?
💡 Hint: Consider the critical nature of activity B.
Question 2
You have identified a project with multiple critical paths. Discuss how you would manage resources effectively across these paths to ensure project completion.
💡 Hint: Think about dependencies and parallel activity management.