Test your understanding with targeted questions related to the topic.
Question 1
Easy
Define cycle time in the context of scraper and pusher operations.
💡 Hint: Think about the steps involved in using the scraper and pusher.
Question 2
Easy
What is one reason why balancing scraper and pusher operations is crucial?
💡 Hint: Consider how idle machines affect productivity.
Practice 4 more questions and get performance evaluation
Engage in quick quizzes to reinforce what you've learned and check your comprehension.
Question 1
What is the primary function of a pusher in earth-moving operations?
💡 Hint: Think about the role each machine plays in a team.
Question 2
Cycle time refers to the total time taken for which process?
💡 Hint: Consider all movements involved.
Solve and get performance evaluation
Push your limits with challenges.
Question 1
A construction site has found that the pusher cycle time needs to reduce to enhance productivity. If currently, the scraper cycle time is 8 minutes and the target is to serve 7 scrapers, calculate the maximum pusher time feasible for balance.
💡 Hint: Balance the equation step-by-step focusing on known variables.
Question 2
After analyzing operations, a project manager sees that running six scrapers reduces turnaround time; however, governing efficiency also demands higher operational costs. Evaluate how the project manager can justify this decision economically.
💡 Hint: Every operational adjustment should relate to higher productivity initially outweighing costs.
Challenge and get performance evaluation