Industry-relevant training in Business, Technology, and Design to help professionals and graduates upskill for real-world careers.
Fun, engaging games to boost memory, math fluency, typing speed, and English skills—perfect for learners of all ages.
Enroll to start learning
You’ve not yet enrolled in this course. Please enroll for free to listen to audio lessons, classroom podcasts and take practice test.
Listen to a student-teacher conversation explaining the topic in a relatable way.
Today, we’ll begin with the angle of swing in excavators. Can anyone tell me what we mean by the angle of swing?
Is it the angle between the bucket when it's digging and where it dumps the material?
Exactly! The angle of swing is the horizontal angle between these two positions. For maximum productivity, we want to aim for a 90-degree angle. Can anyone explain why this is ideal?
Because it minimizes the distance the bucket has to travel?
Correct! Less distance equals less cycle time. Remember this with the acronym **MVP**: Minimize Travel for Velocity Performance!
What happens if the angle goes beyond 90 degrees?
Great question! If the angle increases, the cycle time increases, leading to lower productivity. So, we need to manage our truck placements carefully.
And that ties into the height of cut too, right?
Very much so! Let's recap—ideal conditions exist when the angle of swing is 90 degrees, keeping the cycle time optimal.
Now, let’s discussed height of cut. What does it mean when we say the actual height of cut should match the optimum height?
It means that the depth at which we're digging is optimal for the machine’s efficiency.
That's right! If the depth is less than optimal, we need to apply adjustment factors in our productivity calculations. Who can calculate what happens when it’s less than 100%?
The productivity goes down because we apply correction factors. So if we're only at 60% of the optimum, we might use a correction factor, like 0.91?
Excellent! Always remember to evaluate both the height of cut and the angle of swing together for a complete productivity picture.
This sounds complex! How do we calculate productivity practically?
We will address that shortly. For now, remember the phrase **ACE**: Adjust for Cut Efficiency.
Let’s shift gears. Why is truck spotting clearance important?
It’s so the tail of the excavator doesn’t hit the truck, right?
Exactly! Giving some space for the tail swing is crucial for safe operations. Anyone remember how much distance we should ideally have?
I think enough that the excavator can do a full 360-degree swing without hitting anything!
Spot on! A good rule of thumb is to ensure there's sufficient distance for all types of excavator movements. What’s one way to ensure this is managed well?
By planning our loading setup before starting the job?
Absolutely! Pre-planning is key. Always think of the mnemonic **SAFE**: Secure Area for Fleeting Excavators!
Our last key topic today is haul unit exchange time. What does that mean?
It's the time taken for one loaded truck to leave and an empty one to take its place!
Correct! Minimizing this exchange time maximizes productivity. What happens if this time is too long?
The excavator has to wait around, increasing cycle time!
Right again! To remember this factor, think of **FAST**: Fast Arrivals Sustain Time-savings!
So, is timing really everything?
It really is in this context! To wrap up today’s discussion: Effective management of angle of swing, height of cut, truck positioning, and exchange time are all keys to optimizing productivity in excavator operations.
Read a summary of the section's main ideas. Choose from Basic, Medium, or Detailed.
The section outlines how the angle of swing between an excavator's digging and dumping positions affects cycle time and overall productivity. It explains ideal conditions for maximizing efficiency and introduces adjustment factors based on actual height of cut and swing angle. Important concepts such as haul unit exchange time and the need for proper truck spotting clearance are also highlighted.
This section explores the dynamics of the angle of swing in relation to cycle time for excavators in construction contexts. The angle of swing is defined as the horizontal angle between the digging position and the dumping position of the excavator bucket. It's noted that positioning a truck at a 90-degree angle to the excavator is optimal for efficiency, minimizing cycle time and maximizing productivity.
This section also emphasizes calculating the productivity of the shovel based on the heaped volume of the bucket and applicable correction factors for height and swing. An example calculation reinforces these points, demonstrating how actual working conditions can affect operational efficiency.
Dive deep into the subject with an immersive audiobook experience.
Signup and Enroll to the course for listening the Audio Book
The angle of swing is nothing but the horizontal angle between the digging and the dumping position between the loading and the dumping position.
The angle of swing refers to the horizontal angle created when the bucket of an excavator swings from its loading position to its dumping position. This angle affects how efficiently the excavator can work. A smaller angle means the excavator can operate faster because it doesn’t have to move as far to dump the load. The angle is considered to be optimal at 90 degrees, meaning the truck is aligned perfectly for loading and dumping.
Think of swinging a baseball bat. If you swing the bat directly over the plate (90 degrees), you hit the ball more effectively. If you have to swing out wider (greater than 90 degrees), it takes longer and is less efficient.
Signup and Enroll to the course for listening the Audio Book
As the angle of swing increases, cycle time will increase, and productivity will decrease.
As the angle of swing increases beyond the ideal 90 degrees, the time it takes for the excavator to complete a cycle—swing to load, dump, and return—increases. This directly impacts how many cycles can be completed per hour, thus reducing overall productivity. A larger swing requires more movement, leading to longer waits between loading and unloading.
Imagine playing a game of catch but having to run farther away every time before throwing the ball. The further you are from your partner, the longer it takes each time to get into position and throw, just like the increased cycle time with a larger angle of swing.
Signup and Enroll to the course for listening the Audio Book
The ideal condition for shovel productivity is based on a 90-degree swing.
In ideal conditions, where the excavator's bucket swings at a 90-degree angle, there is optimal efficiency and productivity. This condition assumes the excavator is operating close to the truck, minimizing the distance the bucket needs to swing and thereby reducing the cycle time. It allows for the greatest number of loads to be moved in a given period.
Think of a conveyor belt that transports boxes. When the boxes are placed at the right spot on the belt, they move smoothly and quickly to the next station. If they are placed too far or at an angle, they take longer to get there—just like the excavator's ideal working conditions.
Signup and Enroll to the course for listening the Audio Book
Adjustment factors depend on the actual height of cut of material in your project site and the angle of swing.
When calculating productivity, it's crucial to consider both the height of the cut and the angle of swing. If the actual height differs from the optimum height, correction factors must be applied. For example, if the cut height is lower than expected, productivity decreases, and you adjust calculations according to this factor.
Imagine trying to fill a container with water using a cup. If you only fill the cup halfway (lower than expected), it will take more trips to fill the container, just as lower cut heights reduce the effectiveness of the excavator, requiring more cycles for the same volume of material.
Signup and Enroll to the course for listening the Audio Book
There should be some space left for the tail swing of the shovel, known as truck spotting clearance.
While it is important to place the truck close to the excavator to minimize swing and maximize efficiency, there needs to be adequate space for the shovel’s tail to swing without obstruction. Not allowing for this clearance can lead to accidents or inefficiencies, as the machine might collide with the truck, halting operations.
Imagine a dancer performing on stage. If the performance space is too cramped, the dancer may bump into props or other dancers, disrupting the flow of the performance—similar to the excavator needing room to operate effectively without bumping into obstacles.
Signup and Enroll to the course for listening the Audio Book
The time needed for the loaded truck to leave its position and for a new empty truck to take its place is called haul unit exchange time.
Haul unit exchange time is significant in determining the efficiency of an excavator's operation. If trucks are not readily available, the excavator will have to wait, increasing the total cycle time and reducing productivity. Efficient management of this time is critical to ensure that the excavator always has a truck available to load.
Consider a busy restaurant kitchen where waitstaff must deliver food while chefs prepare meals. If the servers are delayed in returning to get more meals, the kitchen gets backed up, just like if trucks aren’t available for the excavator, it will slow down the entire operation.
Signup and Enroll to the course for listening the Audio Book
The production of shovel depends upon the heaped volume of your bucket, adjusted with the bucket fill factor, divided by the cycle time.
To estimate the productivity of an excavator, one needs to consider the volume of material the bucket can hold (heaped volume) and adjust for how effectively that volume can be filled (bucket fill factor). This total is then divided by the cycle time to find out how much material can be moved in a specified time frame. Increasing bucket efficiency or decreasing cycle time boosts overall productivity.
Think of filling a backpack with books. If the backpack can hold 10 books but is only filled with 6 due to their sizes (fill factor), you aren’t maximizing its capacity. If it takes you 5 minutes to fill it and grab a new one, knowing how many you can fill every hour helps you understand your speed, just like calculating how much an excavator can move.
Learn essential terms and foundational ideas that form the basis of the topic.
Key Concepts
Angle of Swing: The horizontal angle critical for determining cycle time efficiency.
Cycle Time: The time taken for loading and dumping and its impact on productivity.
Height of Cut: The depth affecting the machine's adjusting productivity factors.
Correction Factor: A necessary adjustment for productivity estimates when conditions are not ideal.
Truck Spotting Clearance: Essential space allowing for safe operation of the excavator.
Haul Unit Exchange Time: Key timing that impacts operational efficiency.
See how the concepts apply in real-world scenarios to understand their practical implications.
If a truck is positioned at a 90-degree angle to the excavator, the cycle time is minimized, leading to maximum productivity.
If the actual height of cut is 3.18 meters and the optimum height is 5.3 meters, a correction factor is applied to adjust productivity accordingly.
Use mnemonics, acronyms, or visual cues to help remember key information more easily.
When swings are wide, productivity hides. Keep angles tight, to keep the flow right.
Imagine an excavator like a dancer in a tight space. With every swing at 90 degrees, it glides smoothly, loading its truck without hesitation.
Use HAT to remember: Height And Time for efficient productivity management.
Review key concepts with flashcards.
Review the Definitions for terms.
Term: Angle of Swing
Definition:
The horizontal angle between the digging and dumping positions of the excavator bucket.
Term: Cycle Time
Definition:
The total time taken to complete one full cycle of loading and dumping.
Term: Height of Cut
Definition:
The depth at which material is excavated, ideally matching the optimum height for maximum efficiency.
Term: Correction Factor
Definition:
A value used to adjust productivity estimates based on deviations from ideal operating conditions.
Term: Truck Spotting Clearance
Definition:
The necessary space left for an excavator's tail swing to avoid colliding with a nearby truck.
Term: Haul Unit Exchange Time
Definition:
The time taken for a loaded truck to leave and an empty truck to take its place.