Question 1
Easy
What is the balance number of trucks for a loader if the truck cycle time is 39.5 minutes and the loader cycle time is 5.5 minutes?
💡 Hint: Use the formula: Truck Cycle Time / Loader Cycle Time.
Question 2
Easy
How would you calculate productivity if you have 6 trucks, each with a productivity of 12.53 cubic meters per hour?
💡 Hint: Multiply the number of trucks by each truck's productivity.
Practice 4 more questions and get performance evaluation
Engage in quick quizzes to reinforce what you've learned and check your comprehension.
Question 1
What determines the balance number of trucks?
💡 Hint: Think about the formula for balance number.
Question 2
True or False: Increasing the number of trucks beyond the balance number decreases the total productivity.
💡 Hint: Recall the limitations of loaders when too many trucks are present.
Solve 2 more questions and get performance evaluation
Push your limits with challenges.
Question 1
Calculate the total unit production cost when using the balance number of trucks, including the impact of excessive truck costs beyond this number.
💡 Hint: Use the unit cost formula and consider the effect of productivity limits.
Question 2
Design a scenario where the loader's downtime affects the balance point; suggest solutions to manage this downtime in truck operations.
💡 Hint: Reflect on how to integrate maintenance schedules into operational timelines.