Practice Effect of Trucks on Productivity - 1.4 | 17. Balance Number of Trucks for One Loader | Construction Engineering & Management - Vol 2
K12 Students

Academics

AI-Powered learning for Grades 8–12, aligned with major Indian and international curricula.

Professionals

Professional Courses

Industry-relevant training in Business, Technology, and Design to help professionals and graduates upskill for real-world careers.

Games

Interactive Games

Fun, engaging games to boost memory, math fluency, typing speed, and English skills—perfect for learners of all ages.

Practice Questions

Test your understanding with targeted questions related to the topic.

Question 1

Easy

What is the balance number of trucks for a loader if the truck cycle time is 39.5 minutes and the loader cycle time is 5.5 minutes?

💡 Hint: Use the formula: Truck Cycle Time / Loader Cycle Time.

Question 2

Easy

How would you calculate productivity if you have 6 trucks, each with a productivity of 12.53 cubic meters per hour?

💡 Hint: Multiply the number of trucks by each truck's productivity.

Practice 4 more questions and get performance evaluation

Interactive Quizzes

Engage in quick quizzes to reinforce what you've learned and check your comprehension.

Question 1

What determines the balance number of trucks?

  • Truck Cycle Time divided by Load Cycle Time
  • Loader Speed multiplied by Number of Trucks
  • Cost of Truck Operations

💡 Hint: Think about the formula for balance number.

Question 2

True or False: Increasing the number of trucks beyond the balance number decreases the total productivity.

  • True
  • False

💡 Hint: Recall the limitations of loaders when too many trucks are present.

Solve 2 more questions and get performance evaluation

Challenge Problems

Push your limits with challenges.

Question 1

Calculate the total unit production cost when using the balance number of trucks, including the impact of excessive truck costs beyond this number.

💡 Hint: Use the unit cost formula and consider the effect of productivity limits.

Question 2

Design a scenario where the loader's downtime affects the balance point; suggest solutions to manage this downtime in truck operations.

💡 Hint: Reflect on how to integrate maintenance schedules into operational timelines.

Challenge and get performance evaluation