1.3 - Job Production Estimation
Enroll to start learning
You’ve not yet enrolled in this course. Please enroll for free to listen to audio lessons, classroom podcasts and take practice test.
Interactive Audio Lesson
Listen to a student-teacher conversation explaining the topic in a relatable way.
Understanding Cycle Times
🔒 Unlock Audio Lesson
Sign up and enroll to listen to this audio lesson
Let’s begin by discussing the cycle times for trucks and loaders. Can anyone tell me what the truck cycle time is?
Is it 39.5 seconds?
Exactly! And what about the loader cycle time?
It’s 5.5 seconds.
Great! So, if we want to calculate the balance number of trucks needed for one loader, what formula should we use?
We divide the truck cycle time by the loader cycle time!
Correct! And how does this reflect on our operation's productivity?
It shows how many trucks are optimal for loading efficiently.
Exactly. Remember, we use the formula `Balance Number = Truck Cycle Time / Loader Cycle Time`. Keep this in mind!
Calculating Productivity
🔒 Unlock Audio Lesson
Sign up and enroll to listen to this audio lesson
Now that we’ve calculated the balance number, who can remind us what happens to productivity as we increase truck numbers?
It increases until we reach the balance number.
Right! What happens if we exceed the balance number?
The trucks might start to wait for the loader, so productivity won’t increase beyond a point.
Exactly! The loader's capacity becomes the controlling factor. Beyond what balance number can we not go? Remember it’s around 7.18 trucks?
Yes! We should round it down to 7 to optimize costs.
Great answer! This helps in managing costs effectively. The loader’s throughput is the limit past the balance number.
Economic Analysis of Truck Numbers
🔒 Unlock Audio Lesson
Sign up and enroll to listen to this audio lesson
Let’s shift our focus to the economic implications of our choices. How do we determine the total hourly cost for various truck combinations?
We multiply the number of trucks by the hourly cost and add the loader’s hourly cost.
That's right! For example, if we use 5 trucks, what’s our calculation?
5 multiplied by 1650 plus 2700, which equals 10950 rupees.
Perfect! Now how do we find the unit production cost?
It’s the total cost divided by productivity.
Exactly! Once we calculate the costs for various truck amounts, we can analyze them to find the best combination for minimal unit cost.
Limitations Beyond Balance Number
🔒 Unlock Audio Lesson
Sign up and enroll to listen to this audio lesson
Let’s discuss the implications of exceeding the balance number. What consequences might we encounter?
Increased waiting time for trucks due to insufficient loader availability.
Correct! What happens to the unit production cost in this case?
It goes up because there are fixed costs for more trucks but no increase in productivity.
Exactly! The loader caps productivity and drives costs higher. So, it’s crucial to remain within the balance number for efficiency.
It makes sense—having too many trucks increases costs unnecessarily.
Great observation! This reinforces why it's essential to evaluate economics and balance the machinery for optimization.
Introduction & Overview
Read summaries of the section's main ideas at different levels of detail.
Quick Overview
Standard
In this section, we learn about estimating the number of trucks required for effective loading operations, how the balance number influences productivity, and the economic considerations in determining operational efficiency. Key concepts such as cycle times, productivity calculations, and cost implications are discussed.
Detailed
Job Production Estimation
In this section, we delve into the critical concept of estimating the balance number of trucks necessary for effective loader operation. An initial calculation shows that the balance number of trucks per loader is determined by dividing the truck cycle time by the loader cycle time. Given values are truck cycle time at 39.5 seconds and loader cycle time at 5.5 seconds, leading to a calculated balance of approximately 7.18 trucks.
The estimation process further emphasizes the productivity correlation between the number of trucks and the loader's capabilities – particularly, that the unit production cost is governed by both the number of trucks and operational limitations beyond the balance point. The productivity calculations indicate that while five trucks yield 62.65 cubic meters per hour, increasing to seven trucks raises the output to 87.71 cubic meters per hour, demonstrating direct correlation up to the balance number.
However, exceeding this balance number (for example, moving to eight or nine trucks) starts to halt productivity increases due to waiting times for the loader. Beyond this balance, productivity is dictated by the loader's capacity, leading to an increase in unit production costs without substantial benefits in productivity. The unit costs are calculated using total hourly costs divided by productivity values, revealing that optimum efficiencies align around the balance number.
In conclusion, calculating the appropriate number of trucks is intertwined with understanding the economics of production capacities and ensuring machinery is balanced correctly to reduce excess costs without compromising productivity.
Audio Book
Dive deep into the subject with an immersive audiobook experience.
Balance Number of Trucks Calculation
Chapter 1 of 5
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
To find the balance number of trucks needed for one loader, you calculate the balance number of trucks per loader by dividing the truck cycle time by the loader cycle time. The estimated truck cycle time is 39.5, while the loader cycle time is 5.5, which gives a balance number of 7.18. This number must be rounded to either 7 or 8, depending on economic considerations.
Detailed Explanation
The balance number of trucks indicates how many trucks can efficiently work with one loader. By calculating it using the truck and loader cycle times, we can determine how to maximize productivity. A truck cycle time of 39.5 means that trucks take this long to complete their cycle of loading and unloading, while the loader can load the trucks in 5.5 time units. The division of these two times results in 7.18, meaning either 7 or 8 trucks can be used. The decision between rounding down or up should be based on overall production costs and strategy.
Examples & Analogies
Imagine you're hosting a pizza party. You have one oven that can bake a pizza in 30 minutes and it takes 15 minutes for a delivery person to bring the pizzas to people. If you had to decide how many delivery people (equivalent to trucks) you'd need, you'd realize for every 2 pizzas baked at a time (the loader), only one delivery person is needed to efficiently deliver. If you round down and only use one delivery person, they will always keep busy, ensuring no pizzas are left in the oven unnecessarily.
Impact of Number of Trucks on Productivity
Chapter 2 of 5
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
As you increase the number of trucks from 5 to 9, you can observe how productivity changes. For instance, with 5 trucks, the productivity is 62.65 cubic meters per hour, with 6 trucks it's 75.18, with 7 trucks it's 87.71, and with 8 trucks it's 100.24. However, productivity cannot exceed 90 cubic meters per hour when beyond balance, as trucks will idle waiting for the loader.
Detailed Explanation
This section explains how productivity fluctuates with an increasing number of trucks. When the number of trucks is less than or equal to the balance number, productivity is directly governed by how many trucks are working effectively with the loader. The figures demonstrate that increasing trucks raises productivity up to the loader's maximum of 90 cubic meters per hour. Beyond this balance number, even adding more trucks leads to wasted time as they will wait for the loader to become available, thus not completing any additional work.
Examples & Analogies
Think about a restaurant kitchen. If several chefs (trucks) can work together but only one serving waiter (loader) is available, adding more chefs after a certain point doesn't speed up serving already prepared dishes. They simply wait for the waiter to take the orders to the customers. Thus, while a few chefs are busy cooking, if the waiter can't keep up, you start seeing delays, just like excessive trucks waiting for a loader.
Calculating Unit Production Cost
Chapter 3 of 5
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
Unit cost is determined by dividing the total cost by productivity. For instance, with 5 trucks, the cost is 10,950 rupees divided by the productivity of 62.65, resulting in 174.78 rupees per cubic meter. Similarly, this calculation continues for 6, 7, 8, and 9 trucks, revealing how costs and productivity interact.
Detailed Explanation
The unit production cost gives insights into how efficient each setup is economically. By calculating the total operational cost for different truck combinations, you can discern which combination delivers the most cost-efficient production. As the number of trucks increases, productivity rises initially, lowering unit costs till the balance point. Beyond this, unit costs start to increase due to the idle time and truck costs not being matched by production gains.
Examples & Analogies
Imagine you're analyzing the cost per meal prepared in a catering service. If you have a few chefs working, and meal delivery is speedy, your cost per meal decreases. However, if you overstaff and meals remain stagnant because they can't be served as quickly as they are cooked, your overall costs per meal start to increase because you're still paying those additional chefs but they are not adding value anymore. Understanding this helps you manage both labor and service efficiency.
Choosing the Right Number of Trucks
Chapter 4 of 5
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
Evaluating whether to round the balance number down (to 7) or up (to 8) depends on the unit costs. The unit production cost at 7 trucks is 162.47 rupees, while at 8 trucks it rises to 176.67 rupees. Therefore, rounding down is advisable for minimizing costs.
Detailed Explanation
Deciding on the right number of trucks requires balancing productivity with cost efficiency. When the analysis reveals that increasing trucks past the balance point does not help in raising productivity but raises costs, it's best to opt for the lower number. This practice minimizes costs while keeping operations effective, reflecting a common practice in economic decisions.
Examples & Analogies
Consider a car rental service that charges you per hour. If you rent one car and it can efficiently serve 5 clients a day, but if you add another car, you can only serve the same amount, your rental cost will increase without adding any value. In this case, you might opt to stick with the one car and consider whether you'll need the second later as your service grows.
Conclusion of Job Production Estimation
Chapter 5 of 5
🔒 Unlock Audio Chapter
Sign up and enroll to access the full audio experience
Chapter Content
In summary, balancing the types of machinery, their capacities, and the number needed is crucial for maximum efficiency in production. Rounding down is often more practical than rounding up, allowing room for breaks for loaders and avoiding idling resources.
Detailed Explanation
The conclusion reinforces the need for effective planning in machinery use. By ensuring that the loader and truck types are compatible, and that the number of trucks meets but does not overly exceed the balance number, you can achieve optimal operational efficiency with minimum idle time and costs. Rounding down avoids the complications of excess costs while ensuring effective use of resources.
Examples & Analogies
Think of organizing a sports event. If you have coaches (loaders) managing players (trucks), and you know how many players can fit into your team without stretching your resources too far. Trying to form too many teams with limited coaching leads to a lack of focused training sessions, which can bog down your event, just like too many trucks waiting for limited loader capacity can hurt production.
Key Concepts
-
Balance Number: The ideal number of trucks to ensure efficient loader utilization.
-
Cycle Time: The time taken for a truck to load and unload, impacting productivity.
-
Unit Cost: Cost per unit of production, determined through total cost and productivity.
Examples & Applications
With 5 trucks, if the productivity is 62.65 cubic meters per hour, then for 6 trucks, productivity increases to 75.18 cubic meters per hour.
The impact of exceeding the balance number is evident when productivity remains capped at the loader's capacity, limiting gains despite more trucks.
Memory Aids
Interactive tools to help you remember key concepts
Rhymes
A loader and truck make a great pair; keep the balance, avoid despair!
Stories
Imagine a busy construction site where one loader works hard with five trucks moving material. When more trucks arrive, they wait impatiently, feeling stuck—hence, fewer trucks keep productivity flowing freely!
Memory Tools
L-T-B = Loader, Truck, Balance. Always remember: Loader and Truck must function in harmony for success.
Acronyms
P-A-C
Productivity At Capacity. This helps remember that productivity peaks at the balance number.
Flash Cards
Glossary
- Cycle Time
The total time taken for a truck to complete one full loading and unloading cycle.
- Balance Number
The optimal number of trucks required to maintain efficient loading operations without excess waiting time.
- Loader Productivity
The amount of material the loader can move within a specific duration.
- Unit Production Cost
The total cost associated with production divided by the productivity achieved.
- Total Cost
The sum of all costs incurred for operating a specified number of trucks and loaders.
Reference links
Supplementary resources to enhance your learning experience.