Derrick Removal Process - 3.2 | 6. Types of Jib Cranes | Construction Engineering & Management - Vol 3
K12 Students

Academics

AI-Powered learning for Grades 8–12, aligned with major Indian and international curricula.

Professionals

Professional Courses

Industry-relevant training in Business, Technology, and Design to help professionals and graduates upskill for real-world careers.

Games

Interactive Games

Fun, engaging games to boost memory, math fluency, typing speed, and English skills—perfect for learners of all ages.

Interactive Audio Lesson

Listen to a student-teacher conversation explaining the topic in a relatable way.

Introduction to Erection of Tower Cranes

Unlock Audio Lesson

0:00
Teacher
Teacher

Welcome, class! Today, we will learn about the erection of tower cranes, particularly focusing on the climbing cage method. Can anyone tell me why a solid foundation is crucial for a tower crane?

Student 1
Student 1

Maybe because the crane needs stability when lifting heavy loads?

Teacher
Teacher

Exactly, Student_1! A solid foundation ensures stability. We start by preparing a heavy foundation. What do you think comes next after laying the foundation?

Student 2
Student 2

We have to erect the first sections of the crane, right?

Teacher
Teacher

Right! We use a mobile crane to lift the first sections into place. Good job, everyone!

Understanding Climbing Cages

Unlock Audio Lesson

0:00
Teacher
Teacher

Now, let's talk about climbing cages. Student_3, can you explain how a climbing cage assists in the self-erection process?

Student 3
Student 3

The climbing cage provides support and has a hydraulic jack to lift sections higher as the crane grows taller?

Teacher
Teacher

Great explanation! This allows us to add sections without needing another mobile crane after the initial setup. Why is this beneficial?

Student 4
Student 4

It saves time and reduces costs because we don't have to keep bringing in another crane.

Teacher
Teacher

Exactly! It enhances efficiency in tower crane operations.

Dismantling Procedures

Unlock Audio Lesson

0:00
Teacher
Teacher

Let's move on to the dismantling process. What is the first step when dismantling a tower crane with a climbing cage?

Student 1
Student 1

We should remove the trolley part first, then the counterweights?

Teacher
Teacher

Correct! Then we continue to remove the jib and operator cap. Student_2, could you tell me if dismantling without a climbing cage requires different methods?

Student 2
Student 2

Yes, it would require continuous support from a mobile crane until all components are safely removed.

Teacher
Teacher

Nice observation! It's important to plan according to the crane setup.

Height Considerations

Unlock Audio Lesson

0:00
Teacher
Teacher

Now we will discuss how tall a tower crane can stand safely. What happens if we exceed 120 meters?

Student 3
Student 3

I think we need lateral bracing to stabilize it?

Teacher
Teacher

Yes! Beyond 120 meters, we must brace the crane to ensure safety. Student_4, do you recall the maximum height for braced cranes?

Student 4
Student 4

I believe it's 300 meters, and we cannot go beyond even with bracing.

Teacher
Teacher

Exactly right! Understanding these limits is crucial for crane operations.

Introduction & Overview

Read a summary of the section's main ideas. Choose from Basic, Medium, or Detailed.

Quick Overview

This section explains the process of removing and erecting tower cranes using climbing cages and articulated jibs.

Standard

The chapter provides an overview of the tower crane erection process involving climbing cages, detailed steps for adding sections to increase height, and methods for dismantling the crane. It also discusses the importance of structural support and considerations when working at various heights.

Detailed

Derrick Removal Process

This section describes the derrick removal and erection processes for tower cranes, focusing on the role of articulated jibs and climbing cages. Articulated jib cranes allow repositioning of the hinged jibs to convert horizontal reach into vertical height as per requirements.

Erection of Tower Cranes

  • Preparation: The preparation begins with laying down a heavy foundation and erecting the first few sections of the tower crane using a mobile crane.
  • Climbing Cage: The climbing cage, equipped with a hydraulic jack system, allows for the self-erection of the crane.
  • Assembly Steps: The turntable, operator cap, counter jibs, and counterweights must be set up correctly to ensure stability.
  • Self-Erection Process: Once the initial assembly is complete, sections can be added using the trolley action for height adjustment, culminating in a self-erection method.

Dismantling Process

  • Order of Operations: The dismantling of the crane generally follows the reverse order of the erection process and may require additional support from a mobile crane if no climbing cage is available.
  • Height Considerations: It is critical to factor in maximum crane heights (60-120 meters) and appropriate bracing beyond that height.

Climbing Tower Cranes

  • When constructing structures over 300 meters, climbing tower cranes can be used. These cranes can shift along with the structure as it rises, generally housed in the elevator shafts of buildings.

Audio Book

Dive deep into the subject with an immersive audiobook experience.

Introduction to Derrick Removal

Unlock Audio Book

Signup and Enroll to the course for listening the Audio Book

The derrick removal process involves careful planning and execution to ensure safety and efficiency. This process can vary significantly based on the type of crane being used and the conditions of the construction site.

Detailed Explanation

Derrick removal is an essential operation that often takes place after a project has reached its desired height or has been completed. It involves disassembling the crane methodically, ensuring that each component is dealt with systematically for safety. Factors such as weather conditions, site layout, and crane type can affect how this process is carried out.

Examples & Analogies

Think of removing a layer cake. You wouldn't just rip it apart; instead, you'd carefully take off each layer to keep the cake intact. Similarly, in crane removal, each part of the derrick must be taken off carefully to ensure nothing falls and everyone remains safe.

Self-Erection Procedure with Climbing Cage

Unlock Audio Book

Signup and Enroll to the course for listening the Audio Book

The procedure begins by preparing a strong foundation and bolting the initial sections of the tower to it. The climbing cage helps in self-erection, allowing the crane to grow taller as needed.

Detailed Explanation

To start the self-erection process, construction teams first lay a sturdy foundation to support the tower crane. Once this is completed, they can begin bolting the tower's first sections in place. After these initial steps, the climbing cage, which acts as a lifting mechanism, is employed to allow the tower to grow vertically. This process minimizes the need for additional cranes as the project progresses.

Examples & Analogies

Imagine adding levels to a LEGO tower. You start with a solid base and gradually add more pieces as you build higher. Just like in LEGO, the climbing cage supports each additional ‘level’ of the crane, securing it safely as it rises.

Introducing New Sections

Unlock Audio Book

Signup and Enroll to the course for listening the Audio Book

During the self-erection, new sections are added by unbolting the turntable and lifting it with hydraulic jacks to create space for the new section.

Detailed Explanation

As the crane reaches its height requirements, new sections must be continuously added to maintain the structure's integrity. Workers unbolt the turntable at specific points and use hydraulic jacks to lift it, creating the necessary space to introduce the new section. Each new component is then securely bolted to both the existing structure and the turntable.

Examples & Analogies

It's similar to putting together a puzzle. You lift a part of the structure (the turntable), making space for an extra piece (the new section) to fit in. Once that piece is in place, you make sure it is secure, ensuring the overall puzzle remains stable.

Final Steps in Erection and Dismantling

Unlock Audio Book

Signup and Enroll to the course for listening the Audio Book

Once all sections have been added, the process can be reversed during dismantling, requiring careful planning to ensure safety. Without the climbing cage, a mobile crane will be needed for the entire dismantling process.

Detailed Explanation

Upon completing the height adjustment of the crane, dismantling involves reversing the erection process. During dismantling, it is crucial to remove components step by step, often requiring the help of another mobile crane. Without a climbing cage, safely removing higher sections becomes more complex, highlighting the importance of using the right equipment throughout the crane's life cycle.

Examples & Analogies

It's like taking apart a tent after a camping trip. You start with the highest pole first and work your way down. If you have help (like a mobile crane), it makes the process easier and ensures everything comes down without any risk of falling.

Height Considerations and Stability

Unlock Audio Book

Signup and Enroll to the course for listening the Audio Book

The maximum height for free-standing tower cranes is between 60 to 120 meters. Beyond this, proper bracing is necessary to ensure stability and safety.

Detailed Explanation

Free-standing tower cranes can only safely operate within a specific height range due to stability concerns. If a project requires construction at heights above 120 meters, additional bracing must be employed to ensure the crane is securely fastened to the building structure to counteract potential tipping forces.

Examples & Analogies

Think of a tall tree in the wind. If it grows too high without strong roots or support, it may topple over. Tower cranes work the same way; without the right bracing beyond specific heights, they risk falling.

Special Climbing Tower Cranes

Unlock Audio Book

Signup and Enroll to the course for listening the Audio Book

For structures exceeding 300 meters in height, special climbing tower cranes are used. These cranes can grow with the building, providing support at various construction stages.

Detailed Explanation

When constructing particularly tall buildings, standard tower cranes can’t provide enough height as they exceed the safe limits. Instead, climbing tower cranes, which can adapt and change their height as a building progresses, are employed. They attach to completed floors, allowing them to support construction without the increased risk of instability.

Examples & Analogies

Imagine a skyscraper as a tree growing taller and taller. As new branches (floors) form, they provide support not just for themselves but also for the tree's height. Climbing cranes do just that—they adjust and grow as construction continues, maintaining safety and efficiency.

Definitions & Key Concepts

Learn essential terms and foundational ideas that form the basis of the topic.

Key Concepts

  • Climbing Cage: Essential for the self-erection of cranes by using hydraulic systems.

  • Articulated Jib: Allows vertical height adjustment by repositioning horizontal reach.

Examples & Real-Life Applications

See how the concepts apply in real-world scenarios to understand their practical implications.

Examples

  • An articulated jib crane can adjust its horizontal boom to increase hook height based on site requirements.

  • During the self-erection process, a new section is introduced by towing it closer to the main structure using a trolley action.

Memory Aids

Use mnemonics, acronyms, or visual cues to help remember key information more easily.

🎵 Rhymes Time

  • For cranes so tall and high, a strong base is what they'll rely.

📖 Fascinating Stories

  • Imagine a tower crane growing like a plant—starting as a seed in a solid foundation, stretching higher with the aid of climbing cages that lift it as the building rises around it.

🧠 Other Memory Gems

  • F-A-S-T: Foundation, Assemble, Support with Climbing Cage, Transition to Self-Erection.

🎯 Super Acronyms

C-R-A-N-E

  • Climbing
  • Reinforcement
  • Addition
  • New section
  • Efficient.

Flash Cards

Review key concepts with flashcards.

Glossary of Terms

Review the Definitions for terms.

  • Term: Articulated Jib Crane

    Definition:

    A type of crane that can reposition its hinged jibs for greater hook height.

  • Term: Climbing Cage

    Definition:

    A device that helps in the self-erection of a tower crane by using a hydraulic jack system.

  • Term: Counterweights

    Definition:

    Weights used to balance loads on cranes to ensure stability while lifting.

  • Term: SelfErection

    Definition:

    The process of raising the crane structure by adding sections without external cranes.

  • Term: Lateral Bracing

    Definition:

    Support structures installed to stabilize tower cranes that exceed certain heights.